CLUB REBUILD NEWS
CLUB REBUILD TIMELINE
Date | Event |
2018 – mid 2022 | Manly LSC engagement with Northern Beach Council (NBC).
Fundraising taking place – $5M Cth govt. $5M NBC Community Engagement – Stage 1 |
August 22 | Engage Design Consultants – Terroir Architects appointed by Northern Beaches Council |
December 22 – February 23 | Community Engagement – Stage 2 |
10 December 22 | Community engagement stall at Manly LSC
NSW State govt commits $1M funding – taking funding pool to $11M. |
February 23 | Proposed planning meeting with Manly LSC membership, NBC and Terroir Architects |
May 23 | Concept plans revealed by Terroir Architects |
June – Sept 23 | Community Engagement – Stage 3 by reference to concept plans |
Nov – Dec 23 | Finalisation of Concept Design |
Early 24 | Development Application Lodgement with NBC – on exhibition for further community engagement |
Mid 24 | Detailed Design and Construction Certificate |
Mid 24 | Funding confirmed |
Late 24 | Construction |
2025 | Surf Club and public amenities available for community use |
Timeline:
- April 2024 DA lodgement
- April/May 2025 Start Construction
- Mid 2026 Complete